A guide to road construction

City to see 17 construction projects this year

April 18, 2012

The old joke about there being two seasons in Wisconsin - winter and construction - may not seem very funny with nearly 20 road projects on the schedule this year in the city of Brookfield, not including the major work being done along Bluemound Road.

You may already have seen some of it, particularly on Capitol Drive, as crews have started work and delays are taking hold as the weather warms up and people are looking to get out more.

City of Brookfield Public Works Director Tom Grisa said this number of projects isn't unusual and most of the work is being done on side streets.

While there will be road and lane closures, the city can't pinpoint exactly when they will occur - weather and other factors can play a role in how quickly a project progresses. For all projects, local traffic will still be able to traverse the street. However, in some cases, through-traffic will need to go around roadwork for a short distance - none of the closures will cover enough distance to require signed detour routes.

Where: Royalcrest Drive

When: July 30-Oct. 15

What: water main construction

How much: $300,000

Where: Meadow View Drive

When: May 14-Sept. 30

What: water main construction

How much: $789,985

Where: Brookhill Acres

When: April 16-June 22

What: water main construction

How much: $298,669

Where: Bermuda Boulevard

When: May 14-Aug. 22

What: storm sewer construction

How much: $502,650

Where: Kinsey Park

When: to be determined

What: storm sewer construction

How much: $210,000

Where: 126th Street

When: to be determined

What: storm sewer construction

How much: $30,000

Where: Elderlawn/Clairebridge Drive

When: July 30-Aug. 31

What: storm sewer construction

How much: $70,000

Where: St. Therese Boulevard

When: Sept. 3-Sept. 28

What: storm sewer construction

How much: $75,000

Where: Bishop's Woods Court

When: March 15-April 9

What: storm sewer construction

How much: $113,810

10 Where: Gebhardt Road: Brookfield Road to Barker Road

When: Sept. 1-Sept. 29

What: bike path construction

How much: bid not selected yet

11 Where: Gebhardt Road: Calhoun Road to Brookfield Road

When: Nov. 29-TBD

What: bike path construction

How much: $53,728

12 Where: Capitol Drive: 124th Street to Brookfield Road

When: April 2-Nov. 16

What: bike path construction

How much: $400,000

13 Where:Brookfield Road: Capitol Drive to Lisbon Road

When: Oct. 3-Nov. 22

What: bike path construction

How much: $58,362

14 Where: Beaufort Drive and Capitol Drive

When: April 2-Oct. 26

What: intersection improvements

How much: $450,000

15 Where: Calhoun Road and Capitol Drive

When: April 2-Oct. 26

What: intersection improvements

How much: $800,000

16 Where:Bluemound Road and Calhoun Road

When: July 9-Oct. 26

What: intersection improvements

How much: $375,000

17 Where: Sunnyslope Road and Greenfield Road

When: 2012

What: turn lane reconfiguration

How much: $49,828

This site uses Facebook comments to make it easier for you to contribute. If you see a comment you would like to flag for spam or abuse, click the "x" in the upper right of it. By posting, you agree to our Terms of Use.

Suburban News Roundup

E-mail Newsletter

Your link to the biggest stories in the suburbs delivered Thursday mornings.


Enter your e-mail address above and click "Sign Up Now!" to begin receiving your e-mail newsletter
Get the Newsletter!

Login or Register to manage all your newsletter preferences.

Local Crime Map

CONNECT    

Latest Photo Galleries